June 2026 Work

  • Week of June 8 – Paving New Roads Commences
  • Week of June 15 – Parking Lots Scheduled to Reopen, weather permitting
  • Week of June 22 – Rerouted Road Scheduled to open, weather permitting

Work will start again September 27. Work That Remains to be done:

  • Riverwalk installation along the Wepawaug River
  • Additional Islands in the Roads
  • Reconfiguring Libary Parking Lot and Creating Drive through book drop
  • Installation of EV charging stations and accessible features
  • Landscaping
  • Removing Some of the Invasive species and planting living shoreline along the harbor

Work that Has Been Completed

  • Storm drainage and flood mitigation improvements
  • Installation of municipal water line
  • New fire hydrant installation
  • Rerouting portions of Shipyard Lane
  • Parking lot reconfiguration and resizing
  • Traffic calming features and updated signage
    • Speed Bumps
    • Cobblestone Portion of Road
    • Traffic Islands
    • Narrowing of Road
  • Approximately 1,700 linear feet of new sidewalks

Construction Timeline

Interactive Timeline (Accordion Layout)

Recommended display: expandable accordion sections so residents can quickly scan or tap for details.

▶ Phase 1: Pre-Construction & Site Preparation

  • Surveying and utility markings
  • Installation of construction fencing and safety barriers
  • Initial pedestrian detours and construction signage

▶ Phase 2: Infrastructure & Underground Work

  • Storm drainage and flood mitigation improvements
  • Installation of municipal water line
  • New fire hydrant installation near the boat ramp

▶ Phase 3: Roadway, Parking & Traffic Changes

  • Rerouting portions of Shipyard Lane
  • Parking lot reconfiguration and resizing
  • Traffic calming features and updated signage

▶ Phase 4: Sidewalks & Riverwalk Construction

  • Riverwalk installation along the Wepawaug River
  • Approximately 1,700 linear feet of new sidewalks
  • New and improved crosswalks
  • Pavilion and library-area sidewalk repairs

▶ Phase 5: Final Paving & Site Restoration

  • Final paving, striping, and markings
  • Installation of EV charging stations and accessible features
  • Landscaping restoration
  • Final inspections and project close-out

Note: The timeline is subject to change due to weather, permitting, or field conditions. Updates will be posted as phases begin and conclude.

Key Highlights of the Project

  • Improvement of library parking lot safety measures for better access.
  • Construction of a new walkway along the road to enhance pedestrian safety.
  • Upgrades to drainage systems at Fowler Field to prevent flooding issues.

The project is designed to foster community engagement and improve public infrastructure. By prioritizing safety and accessibility, the Founders Walk project aims to create a more inviting space for residents and visitors alike. The local government is committed to keeping the community informed throughout the development process, ensuring transparency and collaboration.

Stay tuned for further updates as we progress with the project, and feel free to reach out with any questions or concerns regarding the improvements.

Frequently Asked Questions

What improvements are planned for the library parking lot?

The project will enhance safety by redesigning the library parking lot, ensuring better traffic flow and visibility for pedestrians and vehicles.

How will the new walkway benefit the community?

The new walkway will provide a safe and accessible route for pedestrians, encouraging walking and improving connectivity between the library and surrounding areas, ultimately enhancing community engagement.

What drainage issues are being addressed at Fowler Field?

The project aims to resolve existing drainage problems at Fowler Field, preventing flooding and ensuring a safer environment for recreational activities.

When will the project be completed?

The project is expected to be completed by the end of the year, with ongoing updates provided to the community throughout the construction process.

How can residents stay informed about project updates?

Residents can stay informed by subscribing to our newsletter, following our social media channels, and checking the project website regularly for the latest news and updates.